MEIL NRPL
Project Highlights
Scope of Work
Client
Length in Km
Pavement Classification
| Role /Type | Details Type |
| EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
| Independent Engineer | M/s ALTINOK Consulting Engineering Inc in JV with M/s SA Infrastructures consultants Pvt Ltd and association with M/s Marsway Engineering Consultancy and Construction Service Pvt Ltd. |
| Agreement Date | 4th May 2023 |
| Appointed Date | 12th Feb 2024 |
| Maintenance Period | 15 Years after commencing |
| COD Construction Period | 24 Months (730 days) from Appointed Date |
| Project Cost | Rs. 564.07 Crores |
| Structures Scope Details | ||
| Sl. No | Type of Structure | Scope (In Nos) |
| 1 | Box Culverts /Structures | 68 |
| 2 | VUP | 02 |
| 3 | LVUP | 01 |
| 4 | VOP | 01 |
| 5 | Minor Bridges | 11 |
| 6 | Major Bridges | 04 |
| Total - Structures | 87 | |
| 7 | Tunnel(M) | 260 M |